Updated: 5/15/2013 Mine Falls Park TrailsThere will be upcoming paving work on Mine Falls trails south of the canal. Dates to be announced.
Work will take place between 7:00 am and 4:00 pm.
The link below provides a map of the trails to be paved this year.
Click here for map. |
|
Updated: 5/12/2013 Gregg Rd – Paving Program WorkRoadwork on Gregg Rd is ongoing. Work is expected to take place during the hours of 7:00 am and 5:00 pm. Expect delays.
Click to see map.
Please contact Project Engineer, Joe Mendola at 589-3120 if you have any questions or concerns.
|
|
Updated: 5/12/2013 Greenwood Dr – Paving Program WorkRoadwork on Greenwood Dr is ongoing. Work is expected to take place during the hours of 7:00 am and 5:00 pm. Expect delays.
Click to see map.
Please contact Project Engineer, Joe Mendola at 589-3120 if you have any questions or concerns.
|
|
Updated: 5/12/2013 Monza Rd – Paving Program WorkRoadwork on Monza Rd is ongoing. Work is expected to take place during the hours of 7:00 am and 5:00 pm. Expect delays.
Click to see map.
Please contact Project Engineer, Joe Mendola at 589-3120 if you have any questions or concerns. |
|
Updated: 5/3/2013 Elaine Dr – Paving Program WorkBeginning on May 2, 2013 there will be road work on Elaine Dr. Work is expected to take place during the hours of 7:00 am and 5:00 pm. Expect delays.
Click to see map.
Please contact Project Engineer, Joe Mendola at 589-3120 if you have any questions or concerns. |
|
Updated: 4/30/2013 Main Street Mast ArmsThe contractor (New England Signal) continues their work on Main Street . They will be taking down the old mast arm poles and rewiring the traffic signals on the new mast arms and poles directly into the traffic control cabinets. They will be performing work of this nature over the course of the next few weeks along sections of Main Street from Amherst St to West Hollis St. They will also be relocating a few cabinets, installing pedestrian countdown signals, and rewiring all of the new traffic signals directly into the traffic control cabinets at each intersection. |
|
Updated: 4/29/2013 Tennyson Ave – Paving Program WorkBeginning on April 30, 2013 there will be road work on Tennyson Ave. Work is expected to take place during the hours of 7:00 am and 5:00 pm. Expect delays.
Click to see map.
Please contact Project Engineer, Joe Mendola at 589-3120 if you have any questions or concerns. |
|
Updated: 4/29/2013 Taylor St – Paving Program WorkBeginning on April 30, 2013 there will be road work on Taylor St. Work is expected to take place during the hours of 7:00 am and 5:00 pm. Expect delays.
Click to see map.
Please contact Project Engineer, Joe Mendola at 589-3120 if you have any questions or concerns. |
|
Updated: 4/17/2013 Harbor Avenue ProjectThe Harbor Avenue Area Project is progressing toward completion. The goal of the project is to have all work completed prior to June 1, 2013. The work to be completed includes milling and final paving of East Otterson Street, Dearborn Street and Bowers Street.
On May 16th there will be milling on Bowers St between Main Street and Dearborn St. This work will occur between 7:00 am and 8:00 am and will require a detour. Click here for detour.
Final paving of East Otterson Street, Bowers Street and Dearborn Street is scheduled for May 20th and 21st. These roads will be closed to thru traffic as needed during the progress of the paving work. Click here for paving area detour.
The remaining work after paving will be the installation of the pavement stripes.
If you have any questions or concerns during this final work, please contact Construction Manager Scott Pollock at 809-0942 or Project Engineer, Bill Keating, at 589-3120.
Thank you for your patience and understanding during this project. |
|
Updated: 4/17/2013 Gas Main Replacement on Franklin And Middle StreetsLIberty Utilities, the gas company, is replacing gas mains on Franklin Street (from Charles to Front Streets) and on Middle Street. This work will be continuing to around the end of the April, 2013.
This announcement will be updated prior to the start of work on the Water and Sewer Replacement Project 2013.
Click here for map. Middle
Click her for map. Franklin
Questions concerning the gas work will be forwarded to Liberty Utilities. Please inform Joe Mendola, Street Construction Engineer, at 589-3124. |
|
Updated: 4/9/2013 Beacon Street - Sewer Main Replacement - April 15, 2013 - July 8, 2013Work on the Beacon Street/Beacon Court project will begin on or around April 29th. The scope of work involves water and sewer replacement on these streets. The gas company, Liberty Utility, will be replacing a short section of gas main on Amherst Street at Beacon Court. They will be perforning that work first, followed by tthe City replacing the sewer mains, and Penninchuck Water Works replacing the water mains.
Click here for map.
Please call William Keating, Wastewater Engineer, at 589-3125 if you have any questions.
|
|
Updated: 4/3/2013 Sewer 2012 Project: Pleasant and Ash Street The remaining construction work on the Water and Sewer project 2012 has started with new water and sewer on Pleasant Street. That work is complete with the exception of the roadway restoration, which will begin on Monday, May 20th. The initial roadway restoration will consist of grinding and base paving the roadway. It should be completed by Thursday, May 23rd, pending favorable weather. Final paving on Pleasant Street will not occur till late summer.
The contractor, Albanese D&S, is also working on the installation of new water and sewer utilities on Ash Street. That work will likely last until the end of May. Note that on Thursday, May 23rd, there will night work to connect the new water to the main on West Hollis Street. Work is anticipated to occur during the hours of 7pm till 5am (expect delays). Following the water and sewer work, the road will be pulverized and base paved. Final paving will not occurr till late summer.
The road will be closed to thru traffic on both Pleasant and Ash Streets during this work. Detour maps are provided below. Local residents will have access the their homes with the exception of when base paving is occurring, the road cannot be driven untill several hours have passed to allow the new pavement to cool properly. When the paving is occurring and residents need to leave within several hours, we ask that residents park their cars on an adjacent street. As a courtesy, the Contractor will attempt to inform any resident with a car in the driveway that they should move their car if they need to leave while the work is occurring.
Click here for map - Pleasant St
Click here for map - Ash St
The City is managing the sewer replacement work and Pennichuck Water Works is handling the water replacement.
This web site will be updated as work progresses.
Thank you for your patience during this important project. Should you have questions, please call William Keating, project engineer, at 589-3125. |
|