2016 Paving Program

The Division of Public Works will be paving several streets in the coming months, contact the Engineering Department for more information.

Download a PDF version of this list here.

Streets Included in the 2016 Paving Contract

Streets From To Status
Blackstone Drive
Amherst Street
End Shim completed. Final paving by the end of October 2016
Bowman Lane
Barnesdale Road Northeastern Blvd Mill completed. Paving by the end of October 2016
Briarcliff Drive
Fordham Drive
White Planes Drive
Shim completed. Final paving by the end of October 2016
Broad Street
Hyannis Street
Broadcrest Lane
Completed
Carter Circle
Custom Street
Circle Completed
Chaucer Road
Spencer Drive
Coleridge Road
Shim completed. Final paving by the end of October 2016
Coleridge Road
Spencer Drive
Chaucer Road
Shim completed. Final paving by the end of October 2016
Custom Street
Tenby Drive
Harris Road
Completed
Daniel Webster Highway, North & Southbound
Adventure Way
Autumn Leaf
Completed
Eleventh Street
Ledge Street
90' from Ledge Street
Mill completed. Paving by the end of October 2016
Fairmount Street Baldwin Street Charles Street Will be paved by the end of October 2016
Flintlocke Drive
End Jill Drive
Completed
Galway Road
Kenmare Road
Raleigh Drive
Will be paved by the end of October 2016
Grenada Circle
Westgate Crossing
Circle Mill completed. Paving by the end of October 2016
Jill Drive
End Harris Road
Completed
Kenmare Drive
Kerry Lane
Raleigh Drive
Shim completed. Final paving by the end of October 2016
Kerry Lane
Raleigh Drive
Raleigh Drive
Shim completed. Final paving by the end of October 2016
Lisa Drive
East Dunstable Road
Lamb Road
Completed
Lone Star Drive
New Searles Road
End Shim completed. Final paving by the end of October 2016
Loring Drive
Yarmouth Drive
End Shim completed. Final paving by the end of October 2016
Nelson Street
Richmond Street
End
Completed
Ninth Street
Ledge Street
Will Street
Mill completed. Paving to be done by the end of October 2016
Pelham Street
Piermont Street
Hyannis Street
Completed
Piermont Street
Nelson Street
Broad Street
Completed
Rene Drive
Main Dunstable
Northeastern Blvd
Shim completed. Final paving by the end of October 2016
Stafford Road
Nottingham Drive
Northeastern Blvd
Shim completed. Final paving by the end of October 2016
Swift Drive
Whitman Road
Chaucer Road
Shim completed. Final paving by the end of October 2016
Tinker Road
White Oak Drive
Beginning of Bend
Shim completed. Final paving by the end of October 2016
Valencia Drive
Wastgate Crossing
Circle Shim completed. Final paving by the end of October 2016
W. Hollis Street
Wellesley Road
Gary Street
Shim completed. Final paving in September 2016
Whitman Road
Spencer Drive
Coleridge Road
Shim completed. Final paving by the end of October 2016
Will Street
Ninth Street
Simon Street
Mill completed. Paving by the end of October 2016

Streets to be Paved as Part of Sewer Rehabilitation Project

Streets From To
Temple Street
E. Hollis Street
Commercial Street